Curb appeal landscaping project – Part 2 – Planning

Curb appeal landscaping project – Part 2 – Planning

March 17, 2019 0 By Michael

A step by step plan for our curb appeal landscaping project

We’ve been working on our curb appeal landscaping project for a couple of weeks now and we’re ready for the next step – planning. We got through our general idea and estimating parts with only some minor brain and eye strain, and as our next step we need to plan out all  the steps so we can make sure everything gets done in time. We also need to make sure we don’t conflict with any of our other projects. Planning any project can be a little bit of a bummer because you don’t get to DO any of the steps, just think about them and write them down. Especially when you’re talking about planning a gardening project. It’s still too cold to do much outside, so we’re focusing on our regular indoor houseplant routine and starting our outdoor plants for spring

Get your self setup for planning

You can do a project plan with your choice of tools. Anything from paper and pencil all the way to a robust tracking tool.  To map out our curb appeal landscaping project plan, we used Microsoft Project because contrary to popular opinion, it’s a good tool and a personal favorite.  Any way you prefer of making a list with dates and showing what has to happen in which order is ideal.

Don’t forget to take life into account

As noted in our garden expansion project planning step, you need  to take holidays or other non-working time into account. You’ll want to prevent the of drama in having to move tasks or try to be creative to pick up any slack. The best thing to do, before writing any of your tasks down is to grab a calendar and look at what times and days will be available for working on your project and blocking out anything where you might have a conflict. Don’t forget to include family time for birthdays and special events, and any extra days you might have to spend on your leaf babies.

Make your plan

Now that we have the structure and critical dates out of the way we can open this bag of snakes and lay them out straight. Similar to our estimate we laid out our tasks for the curb appeal project in buy, build, plant order. we made top level categories called buy, build and plant, figuring we have to buy stuff before we can build with it, and build stuff before we can plant anything. Since we have some competition for our time, in taking care of the vegetable garden we included those tasks in our plan to make sure there was n

Task list

After you get your headings sorted so you can make sense of what all you’re going to be working on, come up with anything that you’ll need to do in that category.  As general rules of thumb a task should be a complete thing to itself, so it can’t be listed in multiple categories unless its something you’re going to do more than once. As an example, you might think mulch might go under both the buy and build area since its both something we have to buy and something we have to install.  The way we accounted for that in our plan is that under Buy, we listed all the items to purchase, and then under build we listed the activity that we’ll do with it.

Here’s our general task list:

Task Name
Curb Appeal Landscaping Project
   Plan Considerations
      Decide key dates
      Research material shipping times
      Check availability for conflicts
      Indoor planting dates
      Thaw date
      Last frost date
   Estimation
      Decide overall project approach
      Make materials list
      Check in house inventory
      Research materials cost
      Blog post / Journal
   Buy
      Mulch
      Plants
      Ground contact lumber
      Lights
   Build
      Level garden area
      Install Mulch
      Install Walkways
      Install Plants
      Install lights
   Plant
      Harden starts outside
      Transplant seedlings
      Direct Sow
Vegetable Garden Update
   Buy
      Planting medium
      Seeds
      Plant stakes
   Build
      Level garden area
      Plant indoors
      Harden indoor plants
      Transplant indoor plants
      Direct Sow outdoor plants

Timing

The order of the list does not drive order of activities strictly but it just gives us the opportunity to write down whatever comes to mind from a task perspective.  We could get down to even higher levels of detail here, as an example, installing the walkway could be broken down into measuring, drawing lines, digging holes, and connecting the planks to the ground. But we decided that wasn’t really needed at this time to make a plan.

Back in our estimate, we thought about, at a really high level, how much time we thought some of these activities would take. We also thought about things like shipping time and took our USDA calendar into account.

Garden plan dates

These tasks are the key to our plan since we’ve made most of our decisions based on our thaw and last frost dates.  If the weather doesn’t cooperate, these are the date’s well change to re-calculate the balance of the plan, since most of everything else works backwards from here.

Other than things like shipping, rather than trying to work out how much time each item on our plan will take us to do, we allocated how much time we want to allow for each task. For example, we know starting our seeds indoors won’t take us a whole day, and it wont take us but an hour or so to make our online purchases (thanks to our list) so as long as it gets done within that day we’re fine.  In a project where you have multiple people working, or have smaller windows of time to work in, it’s better to estimate actual effort here. This time while working through the plan we needed to balance the curb appeal landscaping project with other life activities. So you’ll notice some activities calculated in days and others in hours.  This does funny things in MS Project and we get auto calculated duration for portions of days. You can round these if you like.

Task Name Duration
Curb Appeal Landscaping Project 14.14 days
   Plan Considerations 10.71 days
      Decide key dates 0 days
      Research material shipping times 0 days
      Check availability for conflicts 0 days
      Indoor planting dates 0 days
      Thaw date 0 days
      Last frost date 0 days
   Estimation 0.64 days
      Decide overall project approach 1 hr
      Make materials list 1 hr
      Check in house inventory 1 hr
      Research materials cost 1 hr
      Blog post / Journal 8 hrs
   Buy 12.14 days
      Mulch 2 hrs
      Plants 2 hrs
      Ground contact lumber 2 hrs
      Lights 2 hrs
   Build 8.43 days
      Level garden area 4 hrs
      Install Mulch 2 hrs
      Install Walkways 8 hrs
      Install Plants 2 hrs
      Install lights 2 hrs
   Plant 10.14 days
      Harden starts outside 10 days
      Transplant seedlings 2 hrs
      Direct Sow 2 hrs
Vegetable Garden Update 10 days
   Buy 10 days
      Planting medium 0.07 days
      Seeds 0.07 days
      Plant stakes 1 hr
   Build 9.57 days
      Level garden area 4 hrs
      Plant indoors 2 hrs
      Harden indoor plants 2 hrs
      Transplant indoor plants 4 hrs
      Direct Sow outdoor plants 1 hr

Congratulations! You’re almost done. Planning out your gardening tasks and the time they’ll take is a huge part of the planning process. The last part is setting dates for all your activities. Since you know when your thaw and last frost dates are and you blocked off any non working days, you can start setting dependencies, which should, make your task plan turn into a real garden project plan.

Dependencies

If you’re going to use Microsoft project to do your planning, we’ll share couple of things we learned from an old project manager a long time ago.

  • Always set a dependency for every task. For key tasks add a set of considerations that will allow them to start
  • Finish to Finish (FF) tasks are tasks that can start independently at any time as long as they finish at the same time
  • Finish to Start  (FS) are the default type task, you must finish task A before you start task B
  • Start to start (SS) tasks must start at the same time, but can finish whenever
  • Lead and use lead and lag time to make things land on the dates you want, don’t force an item to occur on a specific date
ID Task Name Predecessors
1 Curb Appeal Landscaping Project
2    Plan Considerations
3       Decide key dates
4       Research material shipping times
5       Check availability for conflicts
6       Indoor planting dates
7       Thaw date
8       Last frost date
9    Estimation
10       Decide overall project approach
11       Make materials list 10FF
12       Check in house inventory 10FF
13       Research materials cost 10FF
14       Blog post / Journal 10,11,12,13
15    Buy
16       Mulch 7FS-4 days
17       Plants 8FS+3 days
18       Ground contact lumber 7FS-4 days
19       Lights 8FS+3 days
20    Build
21       Level garden area 7
22       Install Mulch 7,16
23       Install Walkways 22,18,21
24       Install Plants 23,17
25       Install lights 24,19
26    Plant
27       Harden starts outside 8FS-10 days
28       Transplant seedlings 8
29       Direct Sow 8
30 Vegetable Garden Update
31    Buy
32       Planting medium 6
33       Seeds 6
34       Plant stakes 8
35    Build
36       Level garden area 39FS-6 days
37       Plant indoors 6
38       Harden indoor plants 37FS+6 days
39       Transplant indoor plants 8
40       Direct Sow outdoor plants 8

Dates

So here’s how to read this plan, the task Buy: Mulch must finish before the last frost date so we can level the area and install the mulch on time for transplanting. So we set a dependency on task ID 7 (Last frost date) and added a few days of lead time for shipping. We can of course start this task earlier if we have time (or money) but it must be complete before task 22 (install mulch).  We’re not going to torture you by writing about how every task is linked together,  you are welcome to ask any questions in our comments section or forum about planning your garden project.

Meanwhile, now that we know when we’re available, our milestones, what has to happen in what order and about how long all the things will take, we can start planning out dates.  This is one of the cool parts about using a tool like MS Project. The dates are a total autopilot GPS thing. Once you’ve wired in the previous bits the dates should just line up to your last frost and ground thaw dates and exclude your non working days like magic.

Task Name Predecessors Duration Start Finish
Curb Appeal Landscaping Project 14.14 days Sat 3/9/19 Sat 5/18/19
   Plan Considerations 10.71 days Sat 3/9/19 Wed 5/1/19
      Decide key dates 0 days Sat 3/9/19 Sat 3/9/19
      Research material shipping times 0 days Sat 3/9/19 Sat 3/9/19
      Check availability for conflicts 0 days Sat 3/9/19 Sat 3/9/19
      Indoor planting dates 0 days Sat 3/16/19 Sat 3/16/19
      Thaw date 0 days Sat 4/6/19 Sat 4/6/19
      Last frost date 0 days Wed 5/1/19 Wed 5/1/19
   Estimation 0.64 days Sat 3/9/19 Sat 3/9/19
      Decide overall project approach 1 hr Sat 3/9/19 Sat 3/9/19
      Make materials list 10FF 1 hr Sat 3/9/19 Sat 3/9/19
      Check in house inventory 10FF 1 hr Sat 3/9/19 Sat 3/9/19
      Research materials cost 10FF 1 hr Sat 3/9/19 Sat 3/9/19
      Blog post / Journal 10,11,12,13 8 hrs Sat 3/9/19 Sat 3/9/19
   Buy 12.14 days Sat 3/16/19 Sat 5/18/19
      Mulch 7FS-4 days 2 hrs Sat 3/16/19 Sat 3/16/19
      Plants 8FS+3 days 2 hrs Sat 5/18/19 Sat 5/18/19
      Ground contact lumber 7FS-4 days 2 hrs Sat 3/16/19 Sat 3/16/19
      Lights 8FS+3 days 2 hrs Sat 5/18/19 Sat 5/18/19
   Build 8.43 days Sat 4/6/19 Sat 5/18/19
      Level garden area 7 4 hrs Sat 4/6/19 Sat 4/6/19
      Install Mulch 7,16 2 hrs Sat 4/6/19 Sat 4/6/19
      Install Walkways 22,18,21 8 hrs Sat 4/6/19 Sun 4/7/19
      Install Plants 23,17 2 hrs Sat 5/18/19 Sat 5/18/19
      Install lights 24,19 2 hrs Sat 5/18/19 Sat 5/18/19
   Plant 10.14 days Sun 3/10/19 Sat 5/4/19
      Harden starts outside 8FS-10 days 10 days Sun 3/10/19 Sun 4/28/19
      Transplant seedlings 8 2 hrs Sat 5/4/19 Sat 5/4/19
      Direct Sow 8 2 hrs Sat 5/4/19 Sat 5/4/19
Vegetable Garden Update 10 days Sat 3/16/19 Sat 5/4/19
   Buy 10 days Sat 3/16/19 Sat 5/4/19
      Planting medium 6 0.07 days Sat 3/16/19 Sat 3/16/19
      Seeds 6 0.07 days Sat 3/16/19 Sat 3/16/19
      Plant stakes 8 1 hr Sat 5/4/19 Sat 5/4/19
   Build 9.57 days Sat 3/16/19 Sat 5/4/19
      Level garden area 39FS-6 days 4 hrs Sun 3/31/19 Sun 3/31/19
      Plant indoors 6 2 hrs Sat 3/16/19 Sat 3/16/19
      Harden indoor plants 37FS+6 days 2 hrs Sat 4/13/19 Sat 4/13/19
      Transplant indoor plants 8 4 hrs Sat 5/4/19 Sat 5/4/19
      Direct Sow outdoor plants 8 1 hr Sat 5/4/19 Sat 5/4/19

Status

To sum all of this up, If you’re doing this by hand it’s easy enough to figure, just make sure you don’t double book yourself for unavailable days. and keep your list up to date whenever you working through your planned activities.

A key measurement for the success of any project is to check your status regularly. Its super important to go back to your plan and check off complete tasks or re plan any late tasks.

If you’d like a copy of our project plan to do your own planning, let us know in the comments or on our forums.